Our Long Range plan:
Finalize Purchase and pick up property deed during Trip to CR,
March 2007 - $56,400.00
Apply for Non-Profit Status (called a Society) with attorney, March, 2007 - $1,000
Begin property preparation for building with Roberto, March, 2007
No Cost
Retain architect and submit phase one drawings to build by March, 2007
Obtain final permit from CR Government for phase one of building project
(Multi-Purpose/Great Room) by July, 2007 - $15,000 = 1% of the actual building cost
Raise friends to underwrite PHASE ONE building project (on-going pursuit)
Begin construction for PHASE ONE building with work teams – Sept., 2007 - $150,000
Appeal to churches for mission “work teams” to come for 10 days to assist with the project
Retain architect and submit PHASE TWO drawings to build by June, 2008 - $17,000 = 1%
Obtain final permit from CR Government for phase two building project by November, 2008
Appeal to churches for mission work teams to come for 10 days to assist with the project
Begin construction for PHASE TWO (3 Individual Cottages) – March, 2009 - $170,000
Retain architect and submit phase three drawings to build by January, 2010 - $9,000 = 1%
Obtain final permit from CR Government for PHASE THREE building project by December, 2010
Appeal to churches for mission “work teams” to come for 10 days to assist with the project
Begin construction for PHASE THREE building (2 Individual Cottages) – July, 2011 - $90,000 |
|



 |
|